Thank you for choosing WHC. Below are the tools we will use to manage the project.
| Phase | Focus Area | Start Date | End Date | Duration |
| Phase 1 | Planning & Stakeholder ID | Wed, May 27, 2026 | Wed, June 10, 2026 | 15 Days |
| Phase 2 | Data Gathering & Assessment | Thu, June 11, 2026 | Tue, June 30, 2026 | 20 Days |
| Phase 3 | Strategy & Financial Modeling | Wed, July 1, 2026 | Wed, July 15, 2026 | 15 Days |
| Phase 4 | Refinement & Final Presentation | Thu, July 16, 2026 | Sat, July 25, 2026 | 10 Days |
PROPOSED MAC 60-Day Detailed Project Plan
Phase 1: Planning & Stakeholder Identification
Duration: 15 Days | Dates: May 27, 2026 – June 10, 2026
-
May 27: Project Kickoff. Align on objectives and finalize communication protocols.
-
May 28 – May 29: Draft and finalize the comprehensive 60-day project plan and timeline.
-
June 1 – June 3: Collaborative session with MAC Executive Director and Board to define the target list of key stakeholders (defense contractors, local government officials, military leadership, and community leaders).
-
June 4 – June 5: Configure the online auto-scheduler (Zoom/Calendly) and draft email outreach templates for interviews.
-
June 8 – June 10: Mobilize the Strategic Planning Subcommittee for the initial kickoff meeting. Launch outreach and begin scheduling interviews.
-
Phase 1 Deliverables: Final Project Plan, Approved Stakeholder Target List, Outreach Templates, and Active Scheduling Portal.
Phase 2: Data Gathering & Assessment
Duration: 20 Days | Dates: June 11, 2026 – June 30, 2026
-
June 11 – June 23: Conduct intensive one-on-one qualitative interviews and focus groups via Zoom with approved stakeholders.
-
June 24 – June 25: Analyze regional economic challenges specific to Indian Head and benchmark regional market trends.
-
June 26 – June 29: Synthesize qualitative data from interviews with quantitative market findings to isolate CCMAC’s core “Value Gap” and opportunities.
-
June 30: Draft the official Stakeholder Value Assessment Report and map out the refined core Value Proposition.
-
Phase 2 Deliverables: Completed Stakeholder Interviews, Value Assessment Report, and Defined Value Proposition Framework.
Phase 3: Strategy & Financial Modeling
Duration: 15 Days | Dates: July 1, 2026 – July 15, 2026
-
July 1 – July 6: Draft the core pillars of the 5-Year Strategic Growth Strategy, focusing on advocacy metrics, regional development, and mission support for NSF Indian Head.
-
July 7 – July 9: Construct the initial Operational Excellence Framework, auditing current bylaws and governance structures to map out a scalable future board model.
-
July 10 – July 14: Build the 5-year financial model, embedding diversified revenue streams (membership tier pricing, federal/state grants, corporate defense sponsorships) and matching cash flow projections.
-
July 15: Compile all elements into the initial comprehensive Strategic Plan Draft.
-
Phase 3 Deliverables: 5-Year Strategic Roadmap, Operational Excellence/Governance Framework, and 5-Year Cash Flow Projection Model.
Phase 4: Refinement & Final Submission
Duration: 10 Days | Dates: July 16, 2026 – July 25, 2026
-
July 16 – July 17: Submit the draft to the Strategic Planning Subcommittee for a 48-hour internal review cycle.
-
July 20 – July 21: Facilitate iterative feedback and revision sessions with the Subcommittee to refine operational, political, and financial nuances.
-
July 22 – July 23: Apply final adjustments to the master strategic document and compile the high-impact board presentation deck.
-
July 24 – July 25: Deliver the formal 5-Year Strategic Growth & Sustainability Plan presentation to the MAC Board of Directors for final sign-off.
-
Phase 4 Deliverables: Finalized 5-Year Strategic Plan Document, Master Board Presentation Deck, and Project Closeout.